Project xyz Review Meeting MinutesnAgendan1. Review of project version 1.0 requirements.n2.Definition of project processes.n3. Reviewof project schedule.nParticipants: John Smith, Jane Doe, Jim Dandyn-Itwas decided that the requirements need to be signed off by product marketing.n-Project processes were accepted.n-Project schedule needs to account for scheduled holidays and employee vacation time. Check with HR for specific dates.n-New schedule will be distributed by Friday.n-Next weeks meeting is cancelled. No meeting until 3/23.